Reference

The Project Manager Cheat Sheet

Every formula and KPI a working project manager, planner or PMP candidate needs — written for printing on a single page or pinning above your desk.

Open Q&APMP Bank

Earned Value

KPI / formulaEquationMeaning & example
Planned Value (PV)PV = % planned × BACBudgeted cost of work scheduled at the data date.Example: If 40% of work was planned and BAC = $1M → PV = $400k.
Earned Value (EV)EV = % complete × BACBudgeted cost of work actually completed.Example: 30% complete on a $1M project → EV = $300k.
Actual Cost (AC)AC = sum of all costs incurredActual cost spent to earn the EV.
Schedule Variance (SV)SV = EV − PVNegative = behind schedule (in $).Example: EV 300, PV 400 → SV = −100.
Cost Variance (CV)CV = EV − ACNegative = over budget for the work earned.
Schedule Performance Index (SPI)SPI = EV ÷ PV< 1 = behind schedule.Example: 300 ÷ 400 = 0.75.
Cost Performance Index (CPI)CPI = EV ÷ AC< 1 = over budget.
EAC (typical)EAC = BAC ÷ CPIForecast final cost assuming current performance continues.
EAC (atypical)EAC = AC + (BAC − EV)Used when current variance is a one-off.
EAC (cost & schedule)EAC = AC + [(BAC − EV) ÷ (CPI × SPI)]Most conservative: both indices erode remaining work.
Estimate to Complete (ETC)ETC = EAC − ACForecast cost from data date to completion.
Variance at Completion (VAC)VAC = BAC − EACNegative = forecast overrun.
TCPI (to BAC)TCPI = (BAC − EV) ÷ (BAC − AC)Performance needed to finish at BAC.
TCPI (to EAC)TCPI = (BAC − EV) ÷ (EAC − AC)Performance needed to hit current EAC.

Earned Schedule

KPI / formulaEquationMeaning & example
Earned Schedule (ES)ES = time when current EV was planned to occurTime-based equivalent of EV.
SPI(t)SPI(t) = ES ÷ ATTime-based SPI; remains meaningful late in the project.

Float & CPM

KPI / formulaEquationMeaning & example
Total Float (TF)TF = LS − ES (or LF − EF)Time activity can slip without delaying project finish.
Free Float (FF)FF = ES(successor) − EF(activity)Slip allowed without delaying any successor.
Critical PathPath with TF = 0 (or minimum)Determines the shortest possible duration.
Forward PassEF = ES + DurationCalculates early dates.
Backward PassLS = LF − DurationCalculates late dates from the end.

Forecasting

KPI / formulaEquationMeaning & example
Run-Rate ForecastForecast finish = AT + (Remaining work ÷ Productivity rate)Simple time-to-complete based on observed rate.
S-Curve VarianceVariance = Actual % − Planned %Quick schedule health check at any date.
Burn RateBurn = AC ÷ Time elapsedMonthly cash burn used in cash-flow forecasting.

Risk

KPI / formulaEquationMeaning & example
Expected Monetary Value (EMV)EMV = Probability × ImpactUsed to size contingency from the risk register.
Contingency ReserveSum of EMV for active risksQuantitative basis for cost/time contingency.
Risk ScoreScore = Probability × Impact (1-5 scale)Prioritises register entries on the heat-map.
PERT Estimate(O + 4M + P) ÷ 6Three-point weighted average for duration/cost.
PERT Standard Deviation(P − O) ÷ 6Quantifies estimating uncertainty.

PM Math

KPI / formulaEquationMeaning & example
Communication Channelsn × (n − 1) ÷ 2Number of two-way channels between n stakeholders.
Present ValuePV = FV ÷ (1 + r)^nDiscounting for NPV decisions.
ROIROI = (Gain − Cost) ÷ CostBusiness-case justification.
Payback PeriodPayback = Investment ÷ Annual cash flowYears until break-even.

Delivery KPIs

KPI / formulaEquationMeaning & example
Schedule AdherenceActivities finished on time ÷ Activities plannedReliability of weekly planning.
Productivity Factor (PF)PF = Earned hours ÷ Actual hoursSite labour efficiency.
Change Order RatioChange order value ÷ Contract valueHealth signal for scope discipline.
Safety TRIR(Recordable injuries × 200,000) ÷ Hours workedStandard industry safety metric.
Academy summaries

Deepen the theory

Practitioner-written learning pages with images, technical summaries and links into the calculators.

Open Academy
Featured Academy

Featured Academy learning pages

Hand-picked tracks, pillars and deep-dives — rotated on every refresh so you discover something new each visit.

Browse all Academy
Executive PMO dashboard with KPI tiles and portfolio heatmap
Knowledge pillar

PMO Reporting and Executive Dashboards

How to design PMO reports and executive dashboards that drive decisions instead of just describing status — KPI hierarchies, narrative structure and the cadence that keeps them honest.

Read article
Dark navy timeline graphic showing a delayed construction schedule with critical path impact bands
Knowledge pillar

The Complete Construction Delay Analysis Guide

A complete, practitioner-led walkthrough of construction delay analysis: delay categories, methodologies, claims preparation and mitigation strategies for real EPC and building projects.

Read article
Earned value management S-curves and KPI gauges
Learning track

Earned Value Management Learning Track

A structured EVM track — from the three core curves through SPI, CPI, SV, CV, TCPI and EAC, ending in earned schedule and probabilistic forecasting.

Read article
Dark navy earned value dashboard with glowing S-curves
Learning track

Earned Value Management

From PV / EV / AC to SPI, CPI, EAC, ETC, VAC and TCPI — the full toolkit for measuring and forecasting project performance.

Read article
Dark navy project controls dashboard with Gantt charts and KPIs
Learning track

Project Controls Fundamentals

Scope, schedule, cost, risk, quality and reporting — the six disciplines that hold every successful capital project together, taught from first principles.

Read article
Open glowing editorial book in a dark navy library
Knowledge pillar

Guides and Long-Form Articles

Practitioner-written explainers across EVM, planning, forecasting, risk and PMO design — read as a syllabus or as a refresher.

Read article
Construction productivity charts overlaid on worksite silhouettes
Knowledge pillar

Construction Productivity Management

How to measure, benchmark and improve construction productivity at crew, discipline and project level — and use it as a leading indicator for schedule and cost.

Read article
Risk distribution and mega project silhouette
Knowledge pillar

Risk Management for Mega Projects

How risk management actually works on mega projects — beyond the register, into quantitative analysis, reserve sizing, risk-adjusted forecasts and structured recovery.

Read article
Career roadmap illustration showing planner to PMO director progression
Learning track

Project Controls Career Roadmap

The full ladder from junior planner to PMO director — skills, certifications, salary bands and the lateral moves that compound across a 20-year project controls career.

Read article
Latest Insights

Project intelligence, weekly

Auto-synced from PMMilestone3.com — fresh articles with photos.

View all insights
Enterprise Upgrade

Upgrade to Enterprise-Level Project Intelligence

Discover the Elite Project Controls System — a professional intelligence framework for modern project controls, forecasting, executive reporting, AI PM workflows and risk management.

  • Executive-grade KPI frameworks
  • AI-powered project workflows
  • Forecasting & risk intelligence
  • PMO-ready reporting templates
Buy me a coffee