Category 01
Extension of Time (EOT)
A contractual mechanism granting additional time to the original completion date when delay is caused by events that are not the contractor's risk under the contract.
When it applies
Whenever a delay event impacts the critical path and falls within an EOT clause — typically employer changes, late information, exceptional weather, force majeure or differing site conditions. The EOT preserves the contractor's right to relief from liquidated damages and may, depending on the cause, carry an entitlement to prolongation cost.
Evidence needed
Notice issued within the contractual window, an updated baseline programme, contemporaneous progress records, a delay event log, and a properly executed delay analysis (TIA, windows or impacted as-planned) demonstrating critical-path impact rather than mere float consumption.
Practitioner note
EOTs are won and lost on documentation discipline in the first week, not on legal argument months later. Treat the contractual notice clause as a non-negotiable controls deliverable.
















