PMP Preparation

PMP Question Bank — 120+ practice questions

Exam-style questions written by certified practitioners. Each answer includes a worked explanation and is tagged by knowledge area and difficulty.

Showing 120 of 120 questions.

InitiatingEasyQ1

Which document formally authorises the existence of a project and provides the project manager with authority?

InitiatingMediumQ2

Who develops the project charter?

InitiatingEasyQ3

When should the project manager be assigned?

InitiatingMediumQ4

Which output of Initiating is most useful for early stakeholder engagement?

InitiatingEasyQ5

Which document presents the financial justification for the project?

InitiatingMediumQ6

Which is NOT typically part of the project charter?

InitiatingMediumQ7

What is the purpose of the Identify Stakeholders process?

InitiatingHardQ8

An assumption log is started in which process?

InitiatingEasyQ9

Benefits management plan describes:

InitiatingMediumQ10

Which of these is an enterprise environmental factor?

InitiatingMediumQ11

Which of these is an organisational process asset?

InitiatingHardQ12

A sponsor signs the charter but later asks the PM to change a strategic objective. The PM should first:

PlanningEasyQ13

Which document defines what is included and excluded from the project?

PlanningMediumQ14

The WBS is decomposed to the level of:

PlanningEasyQ15

Which technique decomposes scope hierarchically?

PlanningMediumQ16

Which best describes a milestone?

PlanningMediumQ17

Three-point estimating uses which formula (PERT beta)?

PlanningHardQ18

Standard deviation in PERT is calculated as:

PlanningMediumQ19

What is the primary purpose of the network diagram?

PlanningEasyQ20

What is total float?

PlanningMediumQ21

Schedule compression by adding resources to critical activities is called:

PlanningMediumQ22

Fast-tracking primarily increases which risk?

PlanningEasyQ23

Which estimating technique uses statistical relationships between historical data and other variables?

PlanningEasyQ24

Analogous estimating is:

PlanningMediumQ25

Which is the most accurate estimating technique?

PlanningHardQ26

Reserve analysis distinguishes between:

PlanningMediumQ27

Cost aggregation produces:

PlanningEasyQ28

The Plan Quality Management process focuses on:

PlanningMediumQ29

The cost of quality (COQ) includes:

PlanningMediumQ30

RACI is a type of:

PlanningMediumQ31

Communications channels for n stakeholders:

PlanningMediumQ32

Risk appetite is best described as:

PlanningMediumQ33

EMV is calculated as:

PlanningHardQ34

Which risk response transfers ownership of a threat to a third party?

PlanningMediumQ35

Which is an opportunity response strategy?

PlanningMediumQ36

Plan Procurement Management produces:

PlanningHardQ37

Which contract type carries the highest risk for the seller?

PlanningHardQ38

Which contract type carries the highest risk for the buyer?

PlanningMediumQ39

Stakeholder engagement levels are:

PlanningEasyQ40

The Requirements Traceability Matrix links:

ExecutingEasyQ41

Which process focuses on building, developing and managing the project team?

ExecutingMediumQ42

A team is in the storming stage of Tuckman. Best response?

ExecutingMediumQ43

Co-location is most beneficial because it:

ExecutingEasyQ44

Most effective conflict resolution technique is:

ExecutingMediumQ45

Which is a leadership style focused on empowering teams to take ownership?

ExecutingEasyQ46

Quality assurance focuses on:

ExecutingMediumQ47

A key output of Manage Communications is:

ExecutingMediumQ48

Direct and Manage Project Work produces:

ExecutingMediumQ49

Which is the best response to an unidentified risk that materialises?

ExecutingHardQ50

Implement Risk Responses is in which Process Group?

ExecutingMediumQ51

Conduct Procurements output is:

ExecutingMediumQ52

Manage Stakeholder Engagement focuses on:

ExecutingMediumQ53

Which is a tool of Develop Team?

ExecutingMediumQ54

Which Executing process establishes ground rules and team charter?

ExecutingHardQ55

A team member misses repeated commitments. Best response?

ExecutingMediumQ56

Which is NOT a source of team conflict?

ExecutingEasyQ57

What is the difference between motivation and morale?

ExecutingMediumQ58

Tuckman stages in order:

ExecutingMediumQ59

Which Herzberg category includes pay and working conditions?

ExecutingMediumQ60

Maslow places self-actualisation at:

Monitoring & ControllingEasyQ61

Earned Value SPI = ?

Monitoring & ControllingEasyQ62

Earned Value CPI = ?

Monitoring & ControllingMediumQ63

SV = ?

Monitoring & ControllingMediumQ64

CV = ?

Monitoring & ControllingMediumQ65

EAC assuming typical performance:

Monitoring & ControllingMediumQ66

EAC assuming atypical (one-off) variance:

Monitoring & ControllingHardQ67

TCPI to meet BAC = ?

Monitoring & ControllingMediumQ68

VAC = ?

Monitoring & ControllingEasyQ69

Which is NOT a tool of Control Schedule?

Monitoring & ControllingMediumQ70

Variance analysis is performed in which process?

Monitoring & ControllingMediumQ71

Perform Integrated Change Control output includes:

Monitoring & ControllingHardQ72

EV = 80, PV = 100, AC = 95. SPI = ?

Monitoring & ControllingHardQ73

Same data: CPI = ?

Monitoring & ControllingHardQ74

Same data with BAC = 1000. EAC typical = ?

Monitoring & ControllingMediumQ75

Quality control output includes:

Monitoring & ControllingEasyQ76

Validate Scope produces:

Monitoring & ControllingMediumQ77

A control chart shows a run of seven points above the mean. This indicates:

Monitoring & ControllingMediumQ78

Which chart prioritises problems by frequency?

Monitoring & ControllingMediumQ79

Cause-and-effect diagram is also called:

Monitoring & ControllingMediumQ80

Control Risks is now called:

Monitoring & ControllingMediumQ81

Control Procurements key tools include:

Monitoring & ControllingHardQ82

An approved change request requires updates to which baseline first?

Monitoring & ControllingMediumQ83

Forecasting in Control Costs produces:

Monitoring & ControllingMediumQ84

Trend analysis examines:

Monitoring & ControllingMediumQ85

A negative SV with positive CV typically means:

Monitoring & ControllingMediumQ86

BEI (Baseline Execution Index) measures:

Monitoring & ControllingHardQ87

If CPI = 1.0 and SPI = 0.9, the project is:

Monitoring & ControllingMediumQ88

Work performance reports are produced in:

ClosingEasyQ89

Which process formally ends the project?

ClosingMediumQ90

Lessons learned are documented:

ClosingMediumQ91

Final product or service transition occurs in:

ClosingMediumQ92

Procurement closure precedes administrative closure because:

ClosingEasyQ93

Final report is an output of:

ClosingMediumQ94

Knowledge transfer is part of:

ClosingMediumQ95

Cancelled projects still require:

ClosingMediumQ96

Which is NOT typically an output of closure?

ClosingHardQ97

Customer refuses to sign acceptance at closure. PM should:

ClosingMediumQ98

Phase gate review primarily decides:

ClosingMediumQ99

Benefits realisation typically occurs:

ClosingMediumQ100

The single best source of lessons learned is:

Professional ResponsibilityEasyQ101

A vendor offers the PM an expensive gift. Best response:

Professional ResponsibilityMediumQ102

PMI Code of Ethics core values are:

Professional ResponsibilityMediumQ103

You discover a colleague falsified progress data. You should:

Professional ResponsibilityMediumQ104

You are asked to certify a milestone you know is not complete. You should:

Professional ResponsibilityMediumQ105

Cultural difference makes a team member uncomfortable with public praise. PM should:

Professional ResponsibilityHardQ106

A government client demands an undocumented fee for permit. PM should:

Professional ResponsibilityMediumQ107

PMI requires PMP holders to:

Professional ResponsibilityMediumQ108

Fairness in PMI ethics requires you to:

Professional ResponsibilityHardQ109

You are offered a role where you would have to misrepresent your experience. You should:

Professional ResponsibilityMediumQ110

Your project will pollute a local water source legally but unethically. You should:

AgileEasyQ111

Velocity in agile measures:

AgileMediumQ112

Burndown chart shows:

AgileMediumQ113

Product Owner is responsible for:

AgileMediumQ114

Scrum Master role:

AgileMediumQ115

Definition of Done is set by:

AgileMediumQ116

Daily stand-up duration:

AgileHardQ117

Hybrid project: which earned value technique works best?

AgileMediumQ118

Sprint retrospective focuses on:

ProcurementMediumQ119

A bidder conference is used to:

ProcurementMediumQ120

Make-or-buy analysis is part of:

Academy summaries

Strengthen your fundamentals

Practitioner-written learning pages with images, technical summaries and links into the calculators.

Open Academy
Featured Academy

Featured Academy learning pages

Hand-picked tracks, pillars and deep-dives — rotated on every refresh so you discover something new each visit.

Browse all Academy
Dark navy earned value dashboard with glowing S-curves
Learning track

Earned Value Management

From PV / EV / AC to SPI, CPI, EAC, ETC, VAC and TCPI — the full toolkit for measuring and forecasting project performance.

Read article
Construction productivity charts overlaid on worksite silhouettes
Knowledge pillar

Construction Productivity Management

How to measure, benchmark and improve construction productivity at crew, discipline and project level — and use it as a leading indicator for schedule and cost.

Read article
Dark navy timeline graphic showing a delayed construction schedule with critical path impact bands
Knowledge pillar

The Complete Construction Delay Analysis Guide

A complete, practitioner-led walkthrough of construction delay analysis: delay categories, methodologies, claims preparation and mitigation strategies for real EPC and building projects.

Read article
Open glowing editorial book in a dark navy library
Knowledge pillar

Guides and Long-Form Articles

Practitioner-written explainers across EVM, planning, forecasting, risk and PMO design — read as a syllabus or as a refresher.

Read article
Project forecasting cockpit with probabilistic S-curves
Knowledge pillar

The Complete Guide to Project Forecasting

How professional project controls teams forecast cost, schedule, productivity and cash flow — and how to combine them into a single risk-adjusted view a board can act on.

Read article
Dark navy Gantt chart with glowing critical path
Learning track

Planning and Scheduling

Baseline development, critical path, float erosion, recovery schedules and forensic delay analysis — explained for working planners.

Read article
Dark navy floating glass calculator cards with glowing inputs
Knowledge pillar

Interactive Calculators

More than thirty client-side calculators covering EVM, schedule, risk, construction productivity, contingency, PMO maturity and career planning.

Read article
Career roadmap illustration showing planner to PMO director progression
Learning track

Project Controls Career Roadmap

The full ladder from junior planner to PMO director — skills, certifications, salary bands and the lateral moves that compound across a 20-year project controls career.

Read article
Open notebook with question marks under soft blue light
Knowledge pillar

Q&A and Exam-Style Questions

Concept questions in the style of PMP / PMI examinations, plus practical scenarios from real construction and PMO environments.

Read article
Latest Insights

Project intelligence, weekly

Auto-synced from PMMilestone3.com — fresh articles with photos.

View all insights
Enterprise Upgrade

Upgrade to Enterprise-Level Project Intelligence

Discover the Elite Project Controls System — a professional intelligence framework for modern project controls, forecasting, executive reporting, AI PM workflows and risk management.

  • Executive-grade KPI frameworks
  • AI-powered project workflows
  • Forecasting & risk intelligence
  • PMO-ready reporting templates
Buy me a coffee